Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Five civilians, forest guard killed in police firing near Assam-Meghalaya border

Five civilians, forest guard killed in police firing near Assam-Meghalaya border
According to the Chief Minister, Thal Shadap, 45, Nikhasi Dhar, 65, and Sik Talang 55, died on the spot, while Tal Nartiang, 40 and Chirup Sumer, 40 succumbed to their injuries in the hospital. 

Five civilians, forest guard killed in police firing near Assam-Meghalaya border

I-T dept detects unaccounted transactions exceeding Rs 100 cr across country

I-T dept detects unaccounted transactions exceeding Rs 100 cr across country
The Income Tax Department on Tuesday said that it has unearthed unaccounted transactions exceeding Rs 100 crore during searches on a few groups engaged in jewellery and real estate business across the country in connection with alleged tax evasion.  According to an official, on November 17, the searches were carried out in more than 30 locations spread across Patna, Bhagalpur, Dehri-on-Sone, Lucknow and Delhi.

I-T dept detects unaccounted transactions exceeding Rs 100 cr across country

Police hunts for man who justified Shraddha killing

Police hunts for man who justified Shraddha killing
In the video that is now viral on social media, Rashid can be heard saying that "when one is in a fit of rage, he can cut anyone into 36 pieces, instead of just 35." When asked whether he was justifying the murder, Rashid says that 'It happens'.

Police hunts for man who justified Shraddha killing

CBI files chargesheet against two in Sonali Phogat murder case

CBI files chargesheet against two in Sonali Phogat murder case
Phogat had come to Goa on August 22 and was staying at a hotel in Anjuna.  She felt uneasy that night and the next morning, she was taken to St. Anthony hospital in Anjuna where she was declared brought dead.

CBI files chargesheet against two in Sonali Phogat murder case

Two food and civil supplies controllers held in tender scam in Punjab

Two food and civil supplies controllers held in tender scam in Punjab
Besides, the VB has also initiated proceedings in the court against three accused -- R.K. Singla, Deputy Director with the food and civil supplies, and Pankaj Kumar and Inderjit Singh, both personal assistants of former food and civil supplies minister Ashu -- to declare them as proclaimed offenders.

Two food and civil supplies controllers held in tender scam in Punjab

Nearly 15,000 Indian students taking online classes in Ukrainian universities: Centre to SC

Nearly 15,000 Indian students taking online classes in Ukrainian universities: Centre to SC
On November 11, the Supreme Court had asked the Centre to file an affidavit to inform it about the number of medical students who were pursuing their studies in Ukraine who have been accommodated in other countries. On Tuesday, a bench of Justices Surya Kant and Vikram Nath scheduled the petition filed by Archita and others for further hearing on November 29.

Nearly 15,000 Indian students taking online classes in Ukrainian universities: Centre to SC