Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjab to redress grievances of NRIs from Dec 16

Punjab to redress grievances of NRIs from Dec 16
These programmes will be held in Jalandhar, SAS Nagar (Mohali), Ludhiana, Moga and Amritsar on December 16, 19, 23, 26 and 30, respectively. NRI Affairs Minister Kuldeep Singh Dhaliwal said issues and complaints of NRI Punjabis will be resolved promptly as well as on the spot during these meetings.

Punjab to redress grievances of NRIs from Dec 16

Mehrauli Murder: Aaftab's polygraph test ends, report within two days

Mehrauli Murder: Aaftab's polygraph test ends, report within two days
Earlier on Tuesday, a Delhi court allowed Delhi Police to conduct a narco test on Aaftab on December 1 and 5, after hearing an application moved by the police on this count. Aaftab, during interrogation, was deceptive in nature and tried to mislead the interrogators.

Mehrauli Murder: Aaftab's polygraph test ends, report within two days

No restriction on issuance of new arms licences in Punjab: Official

No restriction on issuance of new arms licences in Punjab: Official
Notably, the drive against glorification of weapons had been launched on the directions of Chief Minister Bhagwant Mann to curb this trend. Under this drive, verification of licensed weapons are being carried out, besides verifying addresses of licensees.

No restriction on issuance of new arms licences in Punjab: Official

Mother-son arrested in Delhi for chopping & dumping husband's body

Mother-son arrested in Delhi for chopping & dumping husband's body
According to the police, the murder occurred on May 30 and so far, six body parts have been recovered while a search is underway for the missing remains. The accused have been identified as Poonam and her son Deepak. Sources said that after chopping Anjan Das's body, the duo had stored the body parts in their fridge and started gradually disposing them.

Mother-son arrested in Delhi for chopping & dumping husband's body

Couple burnt alive in Begusarai; wife dies, man critically injured

Couple burnt alive in Begusarai; wife dies, man critically injured
According to the official, the victim Sanjay Yadav has a property dispute with one Ramesh Yadav in the village Barihari under Chakia police station in the district. The neighbours rushed them to the primary health centre in Chakia where the woman succumbed to her injuries.

Couple burnt alive in Begusarai; wife dies, man critically injured

Mehrauli Murder: Men with swords attack police van carrying Aaftab

Mehrauli Murder: Men with swords attack police van carrying Aaftab
In a video doing rounds on social media, the men could be seen chasing the van carrying Aaftab and managing to open the van's rear door to find a policeman standing inside, in an apparent attempt to attack Aaftab.

Mehrauli Murder: Men with swords attack police van carrying Aaftab