Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Aaftab Amin Poonawalla's judicial custody extended for 14 more days

Aaftab Amin Poonawalla's judicial custody extended for 14 more days
Poonawalla, who killed his live-in partner Shraddha on May 18 and then chopped her body into 35 pieces, is currently lodged in Tihar Jail. On November 26, he was sent to a 13-day judicial custody by the court.

Aaftab Amin Poonawalla's judicial custody extended for 14 more days

Guj rejected those who engage in politics of empty promises and appeasement: Amit Shah

Guj rejected those who engage in politics of empty promises and appeasement: Amit Shah
Reacting to the BJP registering a historic victory in Gujarat, Union Home Minister Amit Shah tweeted that Gujarat had rejected those who engaged in the politics of empty promises and appeasement. Shah said that he salutes the people of Gujarat for the historic win.

Guj rejected those who engage in politics of empty promises and appeasement: Amit Shah

Punjab to speed up drive against illicit liquor trade

Punjab to speed up drive against illicit liquor trade
Stressing on the need to sensitise the common man against the illicit liquor trade for realising the Rangla Punjab mission of the Chief Minister Bhagwant Mann-led government, Kaler said the Excise Department and the excise police would soon launch an awareness campaign against it.

Punjab to speed up drive against illicit liquor trade

Adhir Ranjan, Hardeep Puri cross swords in LS over Ujjwala subsidy

Adhir Ranjan, Hardeep Puri cross swords in LS over Ujjwala subsidy
The drama took place during Question Hour, when BJP MP from Balaghat, Dhal Singh Bisen sought to know from Puri, the quantum of loss faced by the government as several Ujjwala beneficiaries have failed to get a second refill of their cylinders and whether the government will increase the subsidy amount to ensure refill of Ujjwala cylinders.

Adhir Ranjan, Hardeep Puri cross swords in LS over Ujjwala subsidy

NIA arrests terror accused Bikramjit Singh after extradition from Austria

NIA arrests terror accused Bikramjit Singh after extradition from Austria
An NIA official said that Bikramajit had formed a terror group to carry out terror attacks in Punjab along with with his close associates. He was absconding in a terror case lodged by the NIA.

NIA arrests terror accused Bikramjit Singh after extradition from Austria

Sisters burnt to death after falling into tub of hot rice residue in J'khand

Sisters burnt to death after falling into tub of hot rice residue in J'khand
According to sources, hot water (maad) of rice was kept in an open tub after the mid-day meal was cooked in Chhechani Middle School of Sellari Panchayat situated near an Anganwadi centre. The incident took place on November 24 when the victims who studied in the centre wandered near the school ground while playing and fell into the tub.

Sisters burnt to death after falling into tub of hot rice residue in J'khand