Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

US Embassy starts 12-day visa programme; Indians fume

US Embassy starts 12-day visa programme; Indians fume
Among the H and L, the H-1B and L-1 are among the most popular non-immigrant work visas in the US. In October this year, the US Embassy in India released over 1,00,000 appointments for H and L visas for workers and their families to cut down the wait time. 

US Embassy starts 12-day visa programme; Indians fume

22 injured in fire at wedding venue in UP

22 injured in fire at wedding venue in UP
Eight persons who were critically injured people have been admitted to the Orai Medical College in Jalaun district, said police. According to reports, a gas stove lit up by a cook triggered the blaze, which spread to a nearby wooden structure. 

22 injured in fire at wedding venue in UP

Introduced 'healthy substitute' for illegally-brewed homemade liquor, Punjab govt to SC

Introduced 'healthy substitute' for illegally-brewed homemade liquor, Punjab govt to SC
The state government, in a counter-affidavit, said the Excise Department has been regularly carrying out massive enforcement drives against manufacture and use of illicit homemade liquor/spurious liquor.  The state government's response came after the Supreme Court expressed concern at increasing illicit liquor trade in the state. 

Introduced 'healthy substitute' for illegally-brewed homemade liquor, Punjab govt to SC

Nearly 1,30,000 pilgrims used Kartarpur Sahib Corridor to visit Gurdwara Darbar Sahib

Nearly 1,30,000 pilgrims used Kartarpur Sahib Corridor to visit Gurdwara Darbar Sahib
As a precautionary measure to contain and control the spread of Covid-19 pandemic, the Kartarpur Corridor was temporarily suspended from March 16, 2020. With the improvement in the Covid-19 situation, the corridor was reopened to pilgrims on November 17, 2021.

Nearly 1,30,000 pilgrims used Kartarpur Sahib Corridor to visit Gurdwara Darbar Sahib

Mehrauli murder: DNA of Shraddha's bones matches with her father

Mehrauli murder: DNA of Shraddha's bones matches with her father
The blood samples were also recovered, from bathroom and kitchen, by forensic officials in the Chattarpur house, where both Poonawalla and Walkar had shifted on May 15, three days before her murder.

Mehrauli murder: DNA of Shraddha's bones matches with her father

Six killed in Agra-Lucknow expressway crash

Six killed in Agra-Lucknow expressway crash
The injured have been admitted to a nearby hospital. Chief minister Yogi Adityanath has expressed grief at the incident and directed officials to ensure proper treatment to the injured.

Six killed in Agra-Lucknow expressway crash