Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Man held with over Rs 57 lakh in J&K's Kupwara

Man held with over Rs 57 lakh in J&K's Kupwara
Kashmir police tweeted: "During Naka checking at Braripora Handwara, Police apprehended one Syed Irfan Abdullah resident of Laribal, Handwara and recovered cash amounting to Rs 57.43 lakhs concealed in a geyser.

Man held with over Rs 57 lakh in J&K's Kupwara

Air India 'pee gate': 'Unzipping wasn't for sexual desire', accused tells court

Air India 'pee gate': 'Unzipping wasn't for sexual desire', accused tells court
Shankar Mishra, who is accused of urinating on an elderly female co-passenger in a drunken state on a New York-New Delhi Air India flight in November last year, told a Delhi court on Wednesday through his lawyer that 'unzipping' his pants was not for the purpose of 'sexual desire', and hence he cannot be considered as a 'lustful' man.

Air India 'pee gate': 'Unzipping wasn't for sexual desire', accused tells court

Delhi court extends Aaftab's judicial custody by 14 days

Delhi court extends Aaftab's judicial custody by 14 days
On January 6, Poonawala moved an application in the court seeking release of his debit and credit cards, citing need for funds to purchase day-to-day items, as well as warm clothes. Shukla had extended his judicial custody for four more days and ordered to physically produce him in the court on January 10.

Delhi court extends Aaftab's judicial custody by 14 days

Gujarat police searching for robbers who stole Rs 1 crore worth gadgets from moving truck

Gujarat police searching for robbers who stole Rs 1 crore worth gadgets from moving truck
Next day after all the parcels were counted, they realised that from a total 719 parcels, 667 parcels were intact. The robbers had stolen items from 52 parcels, like laptops, tablets, 259 mobile phones, headphones, wrist watches and print rolls worth Rs one crore.

Gujarat police searching for robbers who stole Rs 1 crore worth gadgets from moving truck

Delhi model of development to be adopted: Punjab Health Minister

Delhi model of development to be adopted: Punjab Health Minister
Assuming the charge of Health and Family Welfare Minister here, Balbir Singh, the legislator from Patiala (Rural) who won the 2022 Assembly election by a whopping margin of over 50,000 votes, told the media that health and education are the areas of core concern of the government.

Delhi model of development to be adopted: Punjab Health Minister

'World looking at India with hope', says PM Modi at Pravasi Divas event

'World looking at India with hope', says PM Modi at Pravasi Divas event
After welcoming a large gathering of NRIs, who have arrived here from several countries to participate in the Pravasi Bharatiya Divas, PM Modi said that every Indian-origin person living in foreign countries 'is brand ambassador of India'.

'World looking at India with hope', says PM Modi at Pravasi Divas event