Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Bodies of 3 of the 4 UP youths killed in Nepal plane crash identified

Bodies of 3 of the 4 UP youths killed in Nepal plane crash identified
After the process of identification is over, the bodies will be brought to Ghazipur. On January 16, family members of the four youths were sent to Kathmandu by road with head of Chak Jainab village Vijay Jaiswal, nayab tehsildar and a revenue inspector to claim and bring back the bodies.

Bodies of 3 of the 4 UP youths killed in Nepal plane crash identified

Full dress rehearsal of Republic Day Parade held

Full dress rehearsal of Republic Day Parade held
Also on Monday, Prime Minister Narendra Modi paid tribute to Netaji Subhas Chandra Bose on the occasion of Parakram Jayanti and said: "Today, on Parakram Diwas, I pay homage to Netaji Subhas Chandra Bose and recall his unparalleled contribution to India's history."

Full dress rehearsal of Republic Day Parade held

Punjab CM to dedicate 400 Aam Aadmi Clinics on Jan 27

Punjab CM to dedicate 400 Aam Aadmi Clinics on Jan 27
Finance Minister Harpal Singh Cheema and Health Minister Balbir Singh said the inauguration program would be held in Amritsar on January 27. The Chief Minister will inaugurate the clinics, while AAP convenor and Delhi Chief Minister Arvind Kejriwal will attend the programme as the chief guest.

Punjab CM to dedicate 400 Aam Aadmi Clinics on Jan 27

Drugs worth Rs 11 cr seized in Manipur, two held

Drugs worth Rs 11 cr seized in Manipur, two held
A police official said that during normal checking of vehicles on Sunday night in Imphal, two persons were apprehended and the drugs, smuggled from Myanmar, were recovered from their procession. The drug peddlers, identified as Md. Abdul Salam and Md. Wasim Akram, have been arrested under the Narcotics Drugs and Psychotropic Substances (NDPS) Act.

Drugs worth Rs 11 cr seized in Manipur, two held

Indian police make third arrest in smuggling case

Indian police make third arrest in smuggling case
The bodies of a married couple and their two children, aged three and 11, were found metres from the border on Jan. 19, 2022. Investigators have said they believe the deaths were linked to a human smuggling operation, and a man charged in the U.S. is to stand trial later this year.

Indian police make third arrest in smuggling case

Denied entry, woman delivers baby outside hospital in UP

Denied entry, woman delivers baby outside hospital in UP
A video showing the woman's ordeal has gone viral on social media in which she is seen lying on the ground in a public place. The incident took place on Thursday and the woman, identified as Kalpana, was "turned back without check-up".

Denied entry, woman delivers baby outside hospital in UP