Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

India, Egypt to elevate relations to strategic partnership, take bilateral trade to $12 bn

India, Egypt to elevate relations to strategic partnership, take bilateral trade to $12 bn
He said that both he and President Sisi closely observed the adverse effects on healthcare infrastructure and global supply chains during the Covid pandemic. Modi further elaborated that "there is also immense potential for enhancing security and defence cooperation between us".

India, Egypt to elevate relations to strategic partnership, take bilateral trade to $12 bn

Air India urination case: Shankar Mishra moves Delhi court seeking bail

Air India urination case: Shankar Mishra moves Delhi court seeking bail
The court listed the matter for the next hearing on January 27. On January 21, the Patiala House Court extended Mishra's judicial custody by 14 days. In a recent development, Air India said that the crew made a judgement call to record the matter as a non-reportable in-flight incident for many reasons.

Air India urination case: Shankar Mishra moves Delhi court seeking bail

Punjab witnessing holistic development, says CM Mann at R-Day function

Punjab witnessing holistic development, says CM Mann at R-Day function
Chief Minister Mann vowed to take Punjab to new heights, and added that the government is committed to carve out an egalitarian society which the great martyrs and national leaders had envisioned. Meanwhile, the Chief Minister announced that in order to solve the traffic problem of Bathinda city, an ultramodern bus stand will be constructed on the outskirts of the city.

Punjab witnessing holistic development, says CM Mann at R-Day function

Pune: Bodies found in river last week a case of 'mass murders'

Pune: Bodies found in river last week a case of 'mass murders'
As per preliminary investigations, the motive behind the murders, a senior citizen couple, their daughter, son-in-law and three grandchildren, is believed to be a family feud arising out of certain superstitions.

Pune: Bodies found in river last week a case of 'mass murders'

Jammu-Srinagar highway closed for vehicular traffic

Jammu-Srinagar highway closed for vehicular traffic
The highway is the lifeline of the Kashmir Valley and the main road link connecting Kashmir with the rest of the country. Kashmir-bound trucks laden with essential supplies and other vehicles pass through the highway. Also, fruit-carrying trucks from Kashmir head for rest of the country through this road.

Jammu-Srinagar highway closed for vehicular traffic

Punjab resents non-inclusion of state's tableau in national R-Day parade

Punjab resents non-inclusion of state's tableau in national R-Day parade
Punjab has also been regularly featuring in the tableau parade showcasing the critical importance of this border state with its rich history, colourful and vibrant culture and pivotal point for defining events which shaped the history of the great nation. 

Punjab resents non-inclusion of state's tableau in national R-Day parade