Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Rs 936 cr related to crypto currency attached or seized by ED: Govt

Rs 936 cr related to crypto currency attached or seized by ED: Govt
Besides, five persons have been arrested and six prosecution complaints (PCs) including one supplementary PC have been filed before the Special Court, PMLA in these cases, he stsated.

Rs 936 cr related to crypto currency attached or seized by ED: Govt

Punjab ex-minister Dharamsot arrested

Punjab ex-minister Dharamsot arrested
A spokesperson for the Vigilance Bureau said following investigations of an enquiry a case under the Prevention of the Corruption Act has been registered against Dharamsot. Giving details, he said from March 1, 2016, to March 31, 2022, the income of the former minister and his family was Rs 2,37,12,596 while the expenditure was Rs 8,76,30,888. 

Punjab ex-minister Dharamsot arrested

Amid Adani group row, RBI says banking sector remains resilient

Amid Adani group row, RBI says banking sector remains resilient
The RBI has a Central Repository of Information on Large Credits (CRILC) database system where the banks report their exposure of Rs 5 crore and above which is used for monitoring purposes.

Amid Adani group row, RBI says banking sector remains resilient

Punjab Cabinet approves new industrial policy; to develop 15 industrial parks

Punjab Cabinet approves new industrial policy; to develop 15 industrial parks
A decision to this effect was taken at a meeting of the Cabinet held under the chairmanship of Chief Minister Bhagwant Mann here. A spokesperson for the Chief Minister's Office said the new policy would be applicable for five years from October 17, 2022 and will spur industrial development and generate more employment opportunities.

Punjab Cabinet approves new industrial policy; to develop 15 industrial parks

Cong calls protest on Feb 6 over Hindenburg report on Adani

Cong calls protest on Feb 6 over Hindenburg report on Adani
The group has lost $100 billion since the Hindenberg report came out. All the Pradesh Congress Committees have been requested to issue the necessary instructions to the District Congress Committees so that apart from senior leaders, party functionaries and workers, mobilisation from the BCC, Panchayat and Booth level is ensured in full measure.

Cong calls protest on Feb 6 over Hindenburg report on Adani

Guru Ravidass gave message of humanity welfare: Punjab CM

Guru Ravidass gave message of humanity welfare: Punjab CM
Addressing a gathering before flagging off a train of pilgrims from here to Varanasi to celebrate the Parkash Purab of Guru Ravidass, the Chief Minister, after taking blessings from head of Dera Ballan Sant Baba Niranjan Dass, said the government is duty bound to ensure the wellbeing of the poor.

Guru Ravidass gave message of humanity welfare: Punjab CM