Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Indian government asks people to hug cows on Valentine's Day

Indian government asks people to hug cows on Valentine's Day
Young educated Indians irrespective of their religion typically spend the holiday crowding parks and restaurants, exchanging gifts and holding parties to celebrate like any other Indian festival, especially since India began the process of economic liberalization in the early 1990s.

Indian government asks people to hug cows on Valentine's Day

Repeated scams in AAP regime exposed Punjab CM: Sukhbir

Repeated scams in AAP regime exposed Punjab CM: Sukhbir
Talking to the media here, the SAD President said AAP had loudly proclaimed that it would give jobs on merit to students. "Forget doing this, the manner in which all recruitment conducted by the government has been vitiated and proved AAP does not have the welfare of youth at heart," he said.

Repeated scams in AAP regime exposed Punjab CM: Sukhbir

Gold jewellery worth Rs 5.66 cr seized by Delhi Customs

Gold jewellery worth Rs 5.66 cr seized by Delhi Customs
The official said that acting on an intelligence input, the Custom officers of Air Cargo Complex (ACC) (Import) intercepted a consignment from Dubai that was meant for transshipment to SEZ, Jaipur.

Gold jewellery worth Rs 5.66 cr seized by Delhi Customs

Two Nigerians held for duping woman of Rs 70,000

Two Nigerians held for duping woman of Rs 70,000
On January 31, the victim received another call from a man claiming to be from the Customs Department at the Mumbai airport. The caller further contended that to issue a yellow card to Jordan Rs 55,000 was required and the amount was transferred by the victim to a man, Robert Kang's account.

Two Nigerians held for duping woman of Rs 70,000

Chopped Shraddha's body into more than 17 pieces, Aftab confessed: Charge sheet

Chopped Shraddha's body into more than 17 pieces, Aftab confessed: Charge sheet
According to the charge sheet, after killing Shraddha on May 18 last year, Poonawalla locked their rented accommodation at south Delhi's Chattarpur Pahari area at about 7.45 p.m and went to a nearby hardware shop where he bought a saw, three blades, a hammer and plastic clip.

Chopped Shraddha's body into more than 17 pieces, Aftab confessed: Charge sheet

Showcase 'Brand Punjab' globally, CM asks industrialists

Showcase 'Brand Punjab' globally, CM asks industrialists
Interacting with industrialists during a session organised here, the Chief Minister said Punjabis are known world over for their hard work and entrepreneurship skill. Mann said it is the need of hour to make the state an industrial hub of the country.

Showcase 'Brand Punjab' globally, CM asks industrialists