Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

3 dead, 40 injured in Yamuna Expressway accident

3 dead, 40 injured in Yamuna Expressway accident
The double-decker bus was going from Delhi to Bihar when it hit a divider and overturned on Sunday night. The injured have been sent to the district hospital where they are undergoing treatment.

3 dead, 40 injured in Yamuna Expressway accident

Railways cancel more than 400 trains before Holi

Railways cancel more than 400 trains before Holi
According to the Railways, some trains coming from Barauni to New Delhi, from Howrah Junction to Jabalpur, from Lucknow to Patliputra, the Humsafar Express from Anand Vihar Terminal to Gorakhpur and the Jharkhand Express coming from Hatia to Anand Vihar Terminal have been cancelled.

Railways cancel more than 400 trains before Holi

Extend Delhi excise scam probe to Punjab: Akali Dal

Extend Delhi excise scam probe to Punjab: Akali Dal
Asserting large-scale corruption in the Punjab excise policy, Majithia said like in the case of Delhi, the entire liquor trade had been handed over to two companies and their profit margin had been doubled to facilitate a quid pro quo.

Extend Delhi excise scam probe to Punjab: Akali Dal

Gold biscuits worth Rs 68 lakhs seized at Surat airport

Gold biscuits worth Rs 68 lakhs seized at Surat airport
The sources said that after a flight from Sharjah arrived at the airport, a passenger alerted a Customs officer about a flip cover being left behind on a trolley. Upon checking, the officer recovered 10 gold biscuits, wrapped in the cover.

Gold biscuits worth Rs 68 lakhs seized at Surat airport

Newly-wed couple found dead with stab wounds in Chhattisgarh

Newly-wed couple found dead with stab wounds in Chhattisgarh
The incident took place on Tuesday at Tikrapara area of Raipur. The deceased have been identified as Aslam Ahmed and Kahkasha Bano, the couple got married on February 19 and their wedding reception was scheduled to be held on Tuesday.

Newly-wed couple found dead with stab wounds in Chhattisgarh

NIA raids 70 locations linked to Bishnoi, Bawana & other gangsters

NIA raids 70 locations linked to Bishnoi, Bawana & other gangsters
Lawrence Bishnoi was placed under arrest by the NIA on November 24, 2022 in connection with a case related to conspiracy hatched by terrorists, gangsters and drug smugglers' syndicate to create terror among the public. His arrest was made when he was lodged in the Bhatinda Jail.

NIA raids 70 locations linked to Bishnoi, Bawana & other gangsters