Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Delhi airport witnesses chaos, passengers complain about long waiting hours

Delhi airport witnesses chaos, passengers complain about long waiting hours
As per the latest data, nearly 1.25 crore passengers were carried by the domestic airlines during January, 2023 in the country as against 64 lakh during the same period last year. The passenger load factor or occupancy of the airlines remained on the higher side in the range of 80 to 90 per cent.

Delhi airport witnesses chaos, passengers complain about long waiting hours

Gang of cyber cheats busted in Delhi, 4 arrested

Gang of cyber cheats busted in Delhi, 4 arrested
The accused were identified as Hardeep Harnal (35), a resident of Mohali, Punjab; Himanshu Verma (27), a resident of Sitapur, Uttar Pradesh; Sharafat Ali (29), a resident of Ambala, Haryana; and Sagar Bagga (30), a resident of Rohini in Delhi.

Gang of cyber cheats busted in Delhi, 4 arrested

AI urination case: Accused Shankar Mishra moves Delhi HC against 'unruly passenger' tag

AI urination case: Accused Shankar Mishra moves Delhi HC against 'unruly passenger' tag
Mishra, who was arrested by the Delhi Police from Bengaluru on January 7 for allegedly urinating on a 70-year-old woman while in a drunken state on a flight last November, was granted bail on January 31 by national capital's Patiala House Court.

AI urination case: Accused Shankar Mishra moves Delhi HC against 'unruly passenger' tag

Woman held at IGI with over 2 kg amphetamine

Woman held at IGI with over 2 kg amphetamine
NCB Deputy Director General Gyaneshwar Singh said the woman was identified as Syeeda Abida. She had plans to travel from Delhi to Doha by a Qatar Airline flight but was apprehended at IGI Airport on March 10.

Woman held at IGI with over 2 kg amphetamine

Amritsar gears up for hospitality of G20 delegates

Amritsar gears up for hospitality of G20 delegates
The two sessions of G20 are slated to be held in the state on March 15-17 and March 19-20. The first one is the second G20 Education Working Group Meeting, while the second is a two-day Labour 20 (L20) meeting.

Amritsar gears up for hospitality of G20 delegates

'Not slow paced', SC on trial in Lakhimpur Kheri violence case

'Not slow paced', SC on trial in Lakhimpur Kheri violence case
On January 25, the Supreme Court granted interim bail for eight weeks to Ashish Mishra and directed him to leave Uttar Pradesh within one week of his release from jail. A bench comprising Justices Surya Kant and J.K. Maheshwari directed the sessions judge dealing with the trial of the case to keep apprising it about the future developments of the trial.

'Not slow paced', SC on trial in Lakhimpur Kheri violence case