Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Mumbai woman who chopped mom into pieces made neighbours believe she was 'alive' in Kanpur

Mumbai woman who chopped mom into pieces made neighbours believe she was 'alive' in Kanpur
She has claimed to the police investigators that her mother died under natural circumstances, allegedly due to a fall on December 27. But since she was scared of getting the blame for it, she resorted to a web of lies and deceit to fool the relatives and the neighbours.

Mumbai woman who chopped mom into pieces made neighbours believe she was 'alive' in Kanpur

Six killed in Hyderabad high rise fire

Six killed in Hyderabad high rise fire
The deceased include four women. Seven others were rescued by fire service personnel. Hyderabad District Collector Amoy Kumar said the victims died of suffocation due to the smoke.

Six killed in Hyderabad high rise fire

Excise policy scam: ED summons Sisodia's PA to join probe

Excise policy scam: ED summons Sisodia's PA to join probe
The Enforcement Directorate (ED) on Friday summoned Devender Sharma, the personal assistant of former Delhi deputy chief minister Manish Sisodia, for questioning in connection with the now-scrapped excise policy scam case. Sharma has been asked to appear before the ED on Saturday by 10 a.m.

Excise policy scam: ED summons Sisodia's PA to join probe

Not working for forming next govt, says Punjab CM on one year at helm

Not working for forming next govt, says Punjab CM on one year at helm
In a video message on the occasion of completion of one year in office, Mann said the people of the state had given a thumping verdict in favour of the Aam Aadmi Party (AAP) during the Assembly elections held last year.

Not working for forming next govt, says Punjab CM on one year at helm

Lawrence Bishnoi gang member held in Goa

Lawrence Bishnoi gang member held in Goa
North Goa Superintendent of Police Nidhin Valsan said that Panaji Town Police station and Sardarpura Police station (Rajasthan) personnel nabbed wanted criminal Pavan Solanki, a native of Mandor in Rajasthan's Jodhpur.

Lawrence Bishnoi gang member held in Goa

Examine situation at micro level, Centre to six states reporting rising Covid cases

Examine situation at micro level, Centre to six states reporting rising Covid cases
The Health Ministry has advised that state should examine the situation of Covid-19 at micro level (district & sub-districts) and maintain focus on implementation of necessary measures for prompt and effective management of Covid-19 duly ensuring effective compliance with various advisories issued by the Ministry.

Examine situation at micro level, Centre to six states reporting rising Covid cases