Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

14 killed in Indore temple tragedy, President, PM express grief

14 killed in Indore temple tragedy, President, PM express grief
As per the police, the cover over an old stepwell, around 50 to 60 feet deep, on which devotees were standing to offering their prayers, caved in, due to which around 30 people fell into it. Panic spread as people started crying after seeing their beloved gasping for life in the deep well.

14 killed in Indore temple tragedy, President, PM express grief

Bipartisan bill introduced in Senate to fix loopholes in H-1B, L-1 visas

Bipartisan bill introduced in Senate to fix loopholes in H-1B, L-1 visas
The comprehensive overhaul of the H-1B and L-1 visa programmes will protect American workers and crack down on foreign outsourcing companies, which exploit these visa programs to deprive qualified Americans of high-skilled jobs. The two visa programmes were created to complement America's high-skilled workforce.

Bipartisan bill introduced in Senate to fix loopholes in H-1B, L-1 visas

Water cess not applicable in Punjab, clarifies Himachal CM

Water cess not applicable in Punjab, clarifies Himachal CM
During the meeting, the Chief Minister expressed the concern of the state over the proposed water cess on hydropower plants being implemented by the Himachal Pradesh government. Mann said the water cess should not be implemented as it is against the interests of the state.

Water cess not applicable in Punjab, clarifies Himachal CM

Director of defunct gold trading company arrested at Chennai airport

Director of defunct gold trading company arrested at Chennai airport
The police had earlier arrested K. Harish and J. Malathy, who were also directors of the company. Five more people are still at large in the multi-crore cheating case carried out by the company in the state.

Director of defunct gold trading company arrested at Chennai airport

Delhi reports 300 Covid cases, positivity rate nears 14%

Delhi reports 300 Covid cases, positivity rate nears 14%
Two Covid-19-related deaths have also been reported in the same time span. The positivity rate of the city has risen to 13.79 per cent. The number of active cases stands at 806 out of which 452 patients are being treated in home isolation.

Delhi reports 300 Covid cases, positivity rate nears 14%

38 school girls test Covid positive in UP's Lakhimpur Kheri

38 school girls test Covid positive in UP's Lakhimpur Kheri
Lakhimpur Kheri Chief Medical Officer (CMO), Santosh Gupta, said that one staff member was also found Covid-positive during a contact tracing exercise on Sunday after which the entire campus has been turned into a quarantine centre by the Health department. This is the highest number of new Covid cases reported in a district in a day this year.

38 school girls test Covid positive in UP's Lakhimpur Kheri