Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

India logs 5,676 new Covid case

India logs 5,676 new Covid case
On Monday, India reported 5,880 Covid cases and the active caseload was 35,199. The daily positivity rate was at 2.88 per cent and the weekly positivity rate was 3.81 per cent. The active cases stand at 0.08 per cent and recovery rate currently is 98.73 per cent.

India logs 5,676 new Covid case

Modi will become PM for third time with more than 300 seats: Shah

Modi will become PM for third time with more than 300 seats: Shah
While addressing a rally of BJP workers in Assam' Dibrugarh, Shah also expressed confidence that the BJP will be victorious in at least 12 out of the 14 Lok Sabha seats in the state. According to him, the party is set to win big in the entire northeast, which accounts for a total of 25 seats in Lok Sabha.

Modi will become PM for third time with more than 300 seats: Shah

Punjab CM dedicates renovated Guru Tegh Bahadur Museum

Punjab CM dedicates renovated Guru Tegh Bahadur Museum
The Chief Minister said Guru's supreme sacrifice as protector of 'dharma' was unparalleled in the history of mankind and stands out as an example for humanity. He said this museum is a humble tribute to this great Sikh Guru who made unparalleled sacrifices to uphold the value of righteousness, truth and freedom of faith.

Punjab CM dedicates renovated Guru Tegh Bahadur Museum

Air India flight to London returns to Delhi after unruly passenger 'harms' 2 cabin crew members

Air India flight to London returns to Delhi after unruly passenger 'harms' 2 cabin crew members
The Air India flight AI 111 scheduled to operate on the Delhi-London-Heathrow route returned shortly after departure. An FIR was lodged as the accused person allegedly misbehaved and caused physical harm to two of the cabin crew members.

Air India flight to London returns to Delhi after unruly passenger 'harms' 2 cabin crew members

India reports 5,880 new Covid cases

India reports 5,880 new Covid cases
The daily positivity rate was at 6.91 per cent while weekly positivity rate stood at 3.67 per cent as per the data released by the Ministry. The active caseload currently stands at 35,199. The recovery rate is at 98.73 per cent.

India reports 5,880 new Covid cases

Three arrested for swapping ATM cards to cheat people in Delhi

Three arrested for swapping ATM cards to cheat people in Delhi
The accused were identified as Sonu Kumar, 27, his brother-in-law Sandeep, and Jony alias Rocky, all residents of Haryana. Police said that they have recovered 113 ATMS cards of various bank, and two PayTm machines from the possession of the accused, and claimed to have solved 14 cases of cheating with the trio's arrest.

Three arrested for swapping ATM cards to cheat people in Delhi