Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Delhi court sends gangster Lawrence Bishnoi to 7-day NIA custody

Delhi court sends gangster Lawrence Bishnoi to 7-day NIA custody
The NIA had produced Bishnoi before the court after bringing him to Delhi from Punjab on Monday for questioning in connection with a case registered last year. Bishnoi is currently lodged in Bathinda Central Jail.

Delhi court sends gangster Lawrence Bishnoi to 7-day NIA custody

Excise policy scam: Delhi court reserves order on Sisodia's bail plea in ED case

Excise policy scam: Delhi court reserves order on Sisodia's bail plea in ED case
Special judge M.K. Nagpal of the Rouse Avenue Court will pronounce the order on April 26. On Monday, the court had extended Sisodia's judicial custody by two weeks in the case.The probe agency had also said that the 60 days given to complete the investigation against Sisodia are not over yet.

Excise policy scam: Delhi court reserves order on Sisodia's bail plea in ED case

Now mafia cannot threaten anyone in UP: Yogi

Now mafia cannot threaten anyone in UP: Yogi
The Chief Minister said: "Before 2017, the state was infamous for riots. More than 700 riots rocked the state between 2012 and 2017. But not a single riot broke out after 2017. Earlier, just the names of many districts scared people. Now there is no need to be scared.

Now mafia cannot threaten anyone in UP: Yogi

Excise policy case: Delhi court extends Sisodia's judicial custody by 2 weeks

Excise policy case: Delhi court extends Sisodia's judicial custody by 2 weeks
On April 5, the ED had informed Judge Nagpal that it has found fresh evidence indicating Sisodia's involvement in the alleged excise scam, and the investigation is at a crucial stage. The court had extended AAP leader's custody till April 17 in this case.

Excise policy case: Delhi court extends Sisodia's judicial custody by 2 weeks

3 held at IGIA with 3 kg gold worth Rs 1.68 cr

3 held at IGIA with 3 kg gold worth Rs 1.68 cr
In three separate incidents, the Customs Officials posted at Indira Gandhi International (IGI) Airport have arrested three persons who were supplying 3 kg gold worth Rs 1.68 crore. A Customs Official said that all three are Indian nationals who arrived from Middle East. They were intercepted and held on the basis of intelligence inputs.

3 held at IGIA with 3 kg gold worth Rs 1.68 cr

Another death due to gunshot wound in Bathinda station; seems to be suicide: Army

Another death due to gunshot wound in Bathinda station; seems to be suicide: Army
A soldier died of a gunshot wound at around 4.30 p.m on Wednesday. He was on sentry duty with his service weapon. The weapon and cartridge case from the same weapon was found next to the soldier, it said. The gunshot wound was near the right temporal region. He was immediately evacuated to the Military Hospital, but succumbed to his injuries.

Another death due to gunshot wound in Bathinda station; seems to be suicide: Army