Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

5 soldiers killed as army vehicle catches fire in J&K's Poonch

5 soldiers killed as army vehicle catches fire in J&K's Poonch
"At around 3 p.m., one vehicle of the Indian Army, while moving from Bhimber Gali to Sangiot in Poonch district, caught fire. Further details are being ascertained," Lt. Col. Devender Anand said in a statement.

5 soldiers killed as army vehicle catches fire in J&K's Poonch

Two held in Punjab on charges of human sacrifice

Two held in Punjab on charges of human sacrifice
Balvir Kaur (50) was found injured in the fields near a canal in Ferozepur village on Wednesday morning. She is presently undergoing treatment at PGIMER in Chandigarh.

Two held in Punjab on charges of human sacrifice

Mehrauli murder: Court disposes of Delhi Police's plea against news channel

Mehrauli murder: Court disposes of Delhi Police's plea against news channel
The Delhi Police had filed an application on April 10 and while dealing with it, Additional Sessions Judge Manisha Khurana Kakkar of the Saket Court Complex said that Special Public Prosecutor Amit Prasad had placed on record the Delhi High Court's order dated April 19 directing media channels to not publish or broadcast any content belonging to the charge sheet in the case.

Mehrauli murder: Court disposes of Delhi Police's plea against news channel

India overtakes China to become most populous country: UN report

India overtakes China to become most populous country: UN report
According to the UNFPA's The State of World Population Report, 2023, India's population has reached 1,428.6 million while China's stands at 1,425.7 million -- a difference of 2.9 million. The UN's World Population Prospects 2022 had also projected India to surpass China as the world's most populous country during 2023.

India overtakes China to become most populous country: UN report

Tim Cook greets first customers as Apple debuts India retail store

Tim Cook greets first customers as Apple debuts India retail store
Cook came out from the Mumbai retail store and took selfies with the first Apple buyers who came in big numbers. He welcomed customers at Apple BKC, located at Mumbai's bustling Bandra Kurla Complex (BKC) financial, arts, and entertainment district, at the Jio World Drive Mall.

Tim Cook greets first customers as Apple debuts India retail store

Man makes bomb threat during security check at Delhi airport

Man makes bomb threat during security check at Delhi airport
The incident took place on April 11 when the man, identified as Shiv, was to take a Go First flight (G8-157) to Bagdogra, West Bengal. According to a complaint lodged by the airline staff, when he was asked to open his bag for a mandatory secondary ladder point check, Shiv got agitated and told them that there was a bomb inside his bag.

Man makes bomb threat during security check at Delhi airport