Close X
Friday, November 22, 2024
ADVT 
India

Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

NIA raids 8 locations in UP, Uttarakhand and Punjab in drugs seizure case

NIA raids 8 locations in UP, Uttarakhand and Punjab in drugs seizure case
The National Investigation Agency (NIA) on Tuesday said that it carried out searches at eight locations in Punjab, Uttarakhand, and Uttar Pradesh in a heroin seizure case. An NIA spokesperson here said that the agency sleuths carried out searches at the residences and offices of individuals involved in this case.

NIA raids 8 locations in UP, Uttarakhand and Punjab in drugs seizure case

'Bharat Jodo Yatra 2.0 likely to begin in December, in hybrid mode'

'Bharat Jodo Yatra 2.0 likely to begin in December, in hybrid mode'
Amid demands for the second leg of Bharat Jodo Yatra, Congress sources on Tuesday indicated that the party is considering this and it could commence any time between December 2023 and February 2024, if finalised. A party source indicated that the discussions are on for the second leg of the yatra led by party leader Rahul Gandhi and it might begin in December first week and end before February end next year.

'Bharat Jodo Yatra 2.0 likely to begin in December, in hybrid mode'

Internet services suspended in Pulwama

Internet services suspended in Pulwama
 Internet services have been suspended from Wampora and Hunipora areas of south Kashmir's Pulwama district due to security reasons until November 8, officials said.

Internet services suspended in Pulwama

Clear dues of sugarcane growers, Punjab minister directs mill

Clear dues of sugarcane growers, Punjab minister directs mill
Dues of Rs 41 crore of sugarcane farmers in the Doaba region in Punjab pending against Golden Sandhar Mills Ltd in Phagwara will be cleared by March 31, 2024, state Agriculture Minister Gurmeet Singh Khudian said. The Minister, along with Special Chief Secretary (Agriculture) K.A.P. Sinha, was chairing a meeting with sugarcane farmers led by BKU (Doaba) president Manjit Singh Rai and BKU (Lakhowal) president Harinder Singh here.

Clear dues of sugarcane growers, Punjab minister directs mill

10 nursing students hospitalised following gas leak in Mathura

10 nursing students hospitalised following gas leak in Mathura
At least 10 nursing students were hospitalised and many others complained of breathlessness and vomiting on Friday after inhaling chlorine gas leaking from a cylinder in Mathura district. The gas leakage was detected from a cylinder stored within the Chief Medical Officer's (CMO) office campus in Mathura.

10 nursing students hospitalised following gas leak in Mathura

Delhi bans construction, demolition work to tackle air pollution

Delhi bans construction, demolition work to tackle air pollution
The Delhi government on Friday said that to tackle the problem of increasing pollution in the national capital, construction and demolition works have been banned in the city. Boring, drilling, excavation, and stuffing have been strictly prohibited in construction and demolition sites. There will be a complete restriction on all structural construction work, including building activities. 

Delhi bans construction, demolition work to tackle air pollution