Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Delhi: Nigerians arrested for cheating over 700 victims on matrimonial website

Delhi: Nigerians arrested for cheating over 700 victims on matrimonial website
The accused were identified as Chife Monday (27) and Igwemma Jame (33), both presently residing in Delhi's Nihal Vihar area. Police said that the accused came to India in 2018 and were staying without valid documents.

Delhi: Nigerians arrested for cheating over 700 victims on matrimonial website

Rahul Gandhi moves Gujarat HC for stay on defamation conviction

Rahul Gandhi moves Gujarat HC for stay on defamation conviction
Gandhi, now disqualified as a parliamentarian, was convicted by a magistrate's court on March 23 for his controversial remark, "All thieves have Modi surname," made during a political campaign in Karnataka's Kolar in 2019. 

Rahul Gandhi moves Gujarat HC for stay on defamation conviction

Excise policy scam: Delhi court fixes May 12 to consider CBI's supplementary charge sheet against Sisodia, others

Excise policy scam: Delhi court fixes May 12 to consider CBI's supplementary charge sheet against Sisodia, others
The probe agency also informed the court that Hyderabad-based CA Butchi Babu Gorantla, Arjun Pandey, and Amandeep Singh Dhall were also mentioned as accused in the final report, which also included a list of witnesses and documents that were used as support. 

Excise policy scam: Delhi court fixes May 12 to consider CBI's supplementary charge sheet against Sisodia, others

Five-time Punjab CM Parkash Singh Badal passes away at 95

Five-time Punjab CM Parkash Singh Badal passes away at 95
A media bulletin from the Fortis Hospital said that Parkash Singh Badal was admitted to the hospital on April 16 with acute exacerbation of bronchial asthma. He was shifted to the medical ICU on April 18 as his respiratory condition worsened.

Five-time Punjab CM Parkash Singh Badal passes away at 95

BJP in fray for Jalandhar bypoll on Modi's performance: Amarinder

BJP in fray for Jalandhar bypoll on Modi's performance: Amarinder
Senior Bharatiya Janata Party leader and former Punjab Chief Minister Amarinder Singh on Monday said his party was fighting the Jalandhar by-election on the basis of nine years' "extraordinary performance" of the Central government led by Prime Minister Narendra Modi. 

BJP in fray for Jalandhar bypoll on Modi's performance: Amarinder

Drunk Indian passenger urinates on co-passenger on New York-Delhi flight

Drunk Indian passenger urinates on co-passenger on New York-Delhi flight
According to sources, the accused passenger, who was reportedly under the influence of alcohol, got engaged in an argument with a co-passenger on board American Airlines flight AA 292 and urinated on him.

Drunk Indian passenger urinates on co-passenger on New York-Delhi flight