Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

First batch of 360 Indian evacuees from Sudan reach Delhi

First batch of 360 Indian evacuees from Sudan reach Delhi
As part of the operation, India has positioned two heavy-lift military transport aircraft in the Saudi Arabian city of Jeddah and a naval ship at a key port in violence-hit Sudan as part of its contingency plans to evacuate its stranded nationals.

First batch of 360 Indian evacuees from Sudan reach Delhi

Delhi Police arrest notorious gangster wanted in multiple cases

Delhi Police arrest notorious gangster wanted in multiple cases
Vikrant alias Mental (25), a resident of Sangam Vihar, had recently taken control of Prince Tewatia's gang. He was wanted in three cases, including murder. Police have recovered two automatic pistols, three country-made pistols and 16 bullets from Vikrant's possession.

Delhi Police arrest notorious gangster wanted in multiple cases

Badal, towering leader of Punjab politics, cremated with state honours

Badal, towering leader of Punjab politics, cremated with state honours
He is survived by son and former deputy chief minister Sukhbir Singh Badal and daughter Parneet Kaur and grandchildren. He lost his life-partner, Surinder Kaur, in 2011.

Badal, towering leader of Punjab politics, cremated with state honours

Husband-wife duo arrested for duping over 30 people of crores

Husband-wife duo arrested for duping over 30 people of crores
The accused were identified as Sukhvinder Singh Sahani (51) and his wife Sheetal Sahani (49). The couple was arrested on April 24, after an investigation was initiated into a complaint filed by Rashmi Batra.

Husband-wife duo arrested for duping over 30 people of crores

11 tourists caught with fake Gulmarg Gondola tickets

11 tourists caught with fake Gulmarg Gondola tickets
Officials said that the ticketing squad at the Kongdoori station of Gulmarg Gondola caught 11 tourists from Gujarat along with a local guide, who had come to board the cable car from Kongdoori to Gulmarg on fake and edited tickets.

11 tourists caught with fake Gulmarg Gondola tickets

Inter-state narco cartel busted, over 300 kg cannabis worth Rs 1 cr seized

Inter-state narco cartel busted, over 300 kg cannabis worth Rs 1 cr seized
The police have also recovered over 300 kilograms of cannabis worth more than Rs 1 crore from them.  The accused were identified as Pratap (45), a resident of Rampura in Delhi; Lakhan (23) and Pooran (22) - both residents of Okhla Mod.

Inter-state narco cartel busted, over 300 kg cannabis worth Rs 1 cr seized